Improvement works to the Digue Nord embankment – In progress 2021

  • Type of works: definitive stabilisation of Quai Hirondelle’s foundations, through adjustments and topping up of the embankment and installation of a protective stone layer composed of an anchored steel wire cage filled with small riprap.
  • Contracting authority: Direction des Travaux Publics
  • Project Manager : SETEC Monaco S.A.M.
  • Duration : 24 weeks

Operations and main quantities :

  • Implementation of security and environmental measures and procedures (temporary sediment barrier, acoustic barrier, sound level meter)
  • Anchorage installation;
  • One-off dredging;
  • Earthworks on the dyke core to adjust the embankment : 980m3;
  • Adjustment of ballast embankment bed 1/1 : 335m3;
  • Creation of a 2/5T stop at the foot of the embankment: 510 T;
  • Sealing crossed bars HA20;
  • Laying of stone slabs 3x2x0.5 m : 180 u;
  • Concreting for percolation, keying and scour filling : 120 m3.
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Maintenance of maritime structures – Repair of the foundation of the “parking des pêcheurs”- Monaco - 2023
Monaco
Discover the Trasomar reference