SEA OUTFALL PP330 – LARVOTTO – 2018
SEA OUTFALL PP330 – LARVOTTO – 2018
Nature of the works :
Diversion of the PP330 sea outfall pipe.
Contracting authority :
S.A.M. Anse du Portier
Designer :
BOUYGUES TP MONACO
Duration :
8 months
Operations and main quantities :
- Temporary diversion of the PVC pressure and HDPE pipe diam. 315 : 100 ml
- Removing/installing stone blocks of 4/8T
- Drilling and blasting the concrete protection with a hydraulic hammer
- Removal of an existing steel outfall of diam. 1000
- Transportation of sections of the outfall from La Seyne sur Mer to Monaco (mirror welding of sea outfalls in La Seyne sur Mer)
Steel coating of pipe
Installation of 2 sections of the outfall in HDPE of diam. 1400 : 60 ml
Underwater saddle connections
Cathodic protection of the elements
Concrete protection perpendicular to the future “Port d’Animation” quay: 40m3
Backfill 5/50 : 700T then riprap 4/8T
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Maintenance of maritime structures – Repair of the foundation of the “parking des pêcheurs”- Monaco - 2023
Monaco
Discover the Trasomar reference