Recovery of the moorings of the Port Hercule “La Cloche” – Monaco – 2024

  • Type of works : Redevelopment of the "La Cloche" area – super-yacht mooring
  • Contracting authority : Société d'Exploitation des Ports de Monaco
  • Project manager : Pierre Louis Engineering
  • Time frame : 1 month of work

Operations and main quantities :

  • By sea, from a barge with a 250T "lattice boom" crane on board:
  • Relocation of 2 existing moorings of 500t each composed of 11 donuts of 45t each on a metal base
  • Supply and installation of a 250t mooring consisting of:
  • A metal frame
  • 6 reinforced concrete cubes of 36t each
  • Dimensioning and implementation of cathodic protection by sacrificial anodes
  • Work carried out in an active port
  • Precise installation of the moorings at the DGPS at a depth of 45
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Development of the Portier cove – Monaco – 2024
Monaco
Discover the Trasomar reference