260-ton mooring laying works – Port hercule Monaco – 2022

  • Type of works: Positionning of new mooring for Méga-Yachts
  • Contracting authority: Société d’Exploitation des Ports de Monaco (S.E.P.M)
  • Project manager: EDEIS
  • Duration : 3 weeks

Operations and main quantities :

  • Manufacture of four 45-ton frames: subcontracted to JB.
  • Manufacture of 36-ton ballast: subcontracted to JB. PASTOR
  • Picking up prefabricated lest by seaway
  • Element’s storage on the barge
  • Positioning elements between 40 and 50 m deep
  • Setting up ecological elements on the mooring and the mooring line