Accueil > References / Realisations > Modification work of two mooring lines/buoys – La Ciotat – 2023

Modification work of two mooring lines/buoys – La Ciotat – 2023

  • Type of works : Supply and installation of 2 systems {mooring boxes + mooring system} + tests on the boxes
  • Contracting authority: La Ciotat Shipyards
  • Project manager : Corinthe Ingénierie
  • Time frame : 1 week

Operations and main quantities :

  • Prior inspections of existing chains / dimension survey
  • Engineering for the supply of 2 mooring buoys (10ans 12 m3)
  • Supply of the anchoring system {chain / shakles / swivels},
  • Onshore preparation of the mooring buoys and anchoring system,
  • Installation of the 2 mooring buoys :
  • Mooring n°1 :
  • Mooring depht : 44 m,
  • Mooring buoy : 12 m3,
  • Hook plate + chain + shackles + swivel system,
  • Mooring n°2 :
  • Mooring depth : 36m,
  • Mooring buoy : 10m3
  • Hook plate + chain + shackles + swivel system,
  • 40T traction tests
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Maintenance of maritime structures – Repair of the foundation of the “parking des pêcheurs”- Monaco - 2023
Monaco
Discover the Trasomar reference