Development of the left bank of the Siagne – Mandelieu la Napoule – 2024

  • Type of works : Reinforcement work on the banks of the Siagne on the left bank near the SNCF bridge
  • Contracting authority : City of Mandelieu-la-Napoule
  • Project manager : Egis
  • Time frame : 5.5 months

Operations and main quantities :

  • Combiwall + backfill :
  • 47 piles diameter 864mm, thickness 10mm, length 14.5ml, by sea, in the direct vicinity of the SNCF bridge,
  • 90 L604 sheet piles, length 9ml, by sea,
  • Creation of 94ml of crown beam (reinforcement, formwork, pouring) – width 1.20ml / height 1ml – implementation of needle formwork,
  • Backfilling with 40/80mm ballast – 2,900m3,
  • Installation of geotextile under riprap between -4 and -6m deep – 620m²,
  • Installation of 800-1,200kg riprap blocks for filling a pit – 270m3,
  • Gateway :
  • 2 piles diameter 864mm, thickness 10mm, length 12ml, by land at night – intermediate foundation of the footbridge,
  • Underwater coppicing of the 6 micro foundation piles upstream of the footbridge,
  • Underwater construction of a 3.65m3 concrete block around 6 micro piles (formwork, reinforcement, concrete),
  • Underwater coppicing of the 2 intermediate piles of the footbridge + the 3 downstream foundation piles,
  • Implementation of the intermediate header (4.25T steel) at night, by land (centimetre precision, adjustment by plungers),
  • Implementation of the downstream header (6T steel), by sea (centimetric precision, adjustment by plungers),
  • Implementation of the 2 footbridges (23m, 18.7T / 27.5m, 23T) upstream of the SNCF bridge and under the SNCF bridge, at night,
  • Implementation of 55 pre-slabs on the footbridge,
  • Implementation of a 5.5T ramp for access to the golf course's boat,
  • Reinforcement and pouring of a 165m² slab on the surface of the footbridge
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Development of the Portier cove – Monaco – 2024
Monaco
Discover the Trasomar reference