Accueil
>
References / Realisations
>
Construction of the dike Récifale
Construction of the dike Récifale
Nature of the works :
Construction of an underwater dike located a hundred meters from the shore, to protect the beach of the Beach Hotel from swell.
Contracting authority :
Société des Bains de Mer
Project Manager :
Pierre LOUIS
Duration :
10 months.
Operations and main quantities :
Trenching: 3 300 m3
Supply and transportation by land and installation of a core TVC 10/200kg: 11 300 T
Supply and rocks ranging from 500/800 kg to 6/8T by land and: 34 000 T
Installing stone blocks from the sea: 10 000 T
Main constraints :
Presence of Posidonia meadow around the site area
Site exposed to swell
Location of seawall and fallback areas far from the site
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020