SEA OUTFALL – R280 – FAIRMONT- 2018/2019
SEA OUTFALL – R280 – FAIRMONT- 2018/2019
Type of works :
Installation of sea outfalls for R280 and EP Fairmont Extension networks
Contracting authority :
DIRECTION DES TRAVAUX PUBLICS DE MONACO
Project manager :
BOUYGUES TP MONACO
Duration :
4 phases of work over 2 years
Operations and main quantities :
Laying riprap 1/3T : 2900T
Laying riprap 0.3/1 T : 150 T
Removing/relaying riprap 6/10T
Underwater rock excavation using a pontoon and 120t long-reach excavator: 950m3
Installation and adjustment of material 20/150 : 300T
Underwater dredging work = 150 m3
Adjustment of the outfall base : 2590 m²
Cutting sections 7 and 8 of the outfall pipe at Seyne sur Mer, in Monaco
Installing 1 section of the outfall pipe in HDPE diam. 2500 : 40 ml - 56T for installation n. 4
Installing 3 sections of the outfall pipe in HDPE diam. 2500: 65T for installation n. 2
Installing 2 sections of the outfall pipe in HDPE diam. 1400 : 30T for installation n. 2
Underwater saddle connections
Installation of outfall ballasting collars: 41U
Cathodic protection of the elements
Concrete (Bouchon) ballast’s pipeline: 110m3
Backfill 20/40 : 2500 T
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Maintenance of maritime structures – Repair of the foundation of the “parking des pêcheurs”- Monaco - 2023
Monaco
Discover the Trasomar reference