Logo Trasomar Monaco

Geotextiles tubes reference

Accueil > References / Realisations > REHABILITATION DU COMPLEXE BALNEAIRE DU LARVOTTO GEOTUBES – 2019/2020

REHABILITATION DU COMPLEXE BALNEAIRE DU LARVOTTO GEOTUBES – 2019/2020

  • Nature of the works : Creation of two offshore submerged Breakwater made up of geosynthetic containers located to the right of the Plage du Larvotto.
  • Contracting authority : DIRECTION DES TRAVAUX PUBLICS DE MONACO
  • Project Management : CORINTHE INGENIERIE
  • Duration : 6 months

Operations and main quantities :

  • Demolition of the main dike, evacuation and treatment of the rubble in an authorized landfill: 100 ml of dike for 1200 m³.
  • Preparation of the bottom for the breakwater: 2 400 nets (filled of materials 45/70mm) for 1 460 m² of submarine platform.
  • Supply and installation of textile tubes : 111 ml (x 3 rows).

Main Issues :

  • Works carried out in the protected marine reserve area: Important environnemental constraints Use of not motorised means operating with compressed air.Daily management on the fauna and flora impact.
  • Works carried out in an urban area: Reduction of noise from the works Access Constraints and reduced site area.
FIGHT AGAINST THE EROSION « PLAGE DU RAYOL » EAST/WEST CONSERVATION OF COAST - 2020
Plage du Rayol
Discover the realisation
Maintenance of maritime structures – Repair of the foundation of the “parking des pêcheurs”- Monaco - 2023
Monaco
Discover the Trasomar reference